Case 01 / Brand and domain migration

Gate company logoGate

A full-site brand cutover completed in three weeks

The move from Gate.io to Gate.com touched every customer-facing surface: app, website, campaign pages, social channels, email, support, help center, and multilingual pages. I turned that change into a coordinated three-week cutover.

Project lead / cross-team coordination / risk and validation
Brand migrationRisk controlCutover governance
01 / Project

Gate’s brand and domain migration moved Gate.io to Gate.com across the app, website, campaigns, social channels, email, support, help center, and multilingual pages.

02 / Ownership

As project lead, I coordinated the touchpoint map, owners, cutover windows, risk reviews, validation evidence, and leadership updates.

03 / Constraint

The program began early in my tenure with a three-week window. Any missed or delayed public entry point could affect customers and weaken brand consistency.

04 / Outcome

The full-site migration landed on time with no major incidents. Its control sheet and validation model also informed later portfolio governance work.

01Completed in three weeks
02No major incidents
03Multi-surface and multilingual scope
01

Background

The Gate.io to Gate.com brand and domain migration was one of my first major programs at Gate. It was highly visible from the start and reached across every customer-facing touchpoint.

02

Challenge

The pressure came from synchronization. One lagging touchpoint could easily become the first thing users noticed.

03

My role

I coordinated touchpoints, cutover windows, validation evidence, risk reviews, and leadership visibility across teams.

04

Result

The migration was completed in three weeks without major incidents. It also gave me a fast understanding of Gate’s key operating and cross-functional workflows.

05

Reflection

Large cutovers hold when boundaries, ownership, and validation methods stay clear from start to finish.

Actions

  1. 01Mapped all external touchpoints
  2. 02Defined cutover windows and owners
  3. 03Used screenshots and links as validation evidence
  4. 04Reviewed risks and missed items daily

Systems built

  • Migration control sheet
  • Touchpoint validation flow
  • Daily risk review
  • Leadership progress view